High-rise SFS and aluminium glazing façade for a build to rent residential scheme in the centre of Leeds.

High-rise SFS and aluminium glazing façade for a build to rent residential scheme in the centre of Leeds.
The scope includes Ayrshire SFS, Technal SOLEAL NEXT windows, Technal TITANE doors, and Technal Tental 50TT zone-drained curtain walling, all coordinated under a single package to reduce interface risk and improve buildability.
The project has been delivered under a compressed design programme and strict fire and acoustic performance requirements, including 60-minute fire-rated SFS and enhanced acoustic glazing.
With limited site storage and a tightly sequenced floor-by-floor installation programme, Advanced Glass has maintained programme certainty through careful planning, just-in-time deliveries, and the use of digital and robotic setting-out technology.
Advanced Glass was appointed to deliver both the SFS and glazing packages, providing the client with a single point of responsibility for critical façade elements and reducing interface risk across the building envelope. This also ensured the facade became weather-tight as much as possible during the SFS and window installation, minimising water ingress into the building. This approach enables internal trades to start earlier, reducing the overall construction program.

Advanced Glass has been responsible for the design, supply, and installation of a comprehensive façade and SFS package, including:
A key architectural feature of the project is the use of dual-colour aluminium profiles across the windows, doors, and curtain walling, requiring careful coordination to achieve consistent detailing and finish quality.
One of the primary challenges on Flax Place was the compressed design programme. Advanced Glass was given just four weeks from instruction to complete the full design of both the SFS and window systems.
Fire safety is also a critical consideration. The SFS package was required to achieve a 60-minute fire performance, and through-wall fire safety requirements defined by the fire engineer had to be demonstrated using verified test data.
By delivering multiple packages, façade interfaces were simplified, significantly reducing coordination and logistics challenges that are typically associated with multi-trade façades. There can be no claims for structural opening positions not being at the correct level or in the correct location when a single contractor has sole responsibility.

The project operates under strict logistical constraints, with no dedicated laydown area. All materials are delivered on a just-in-time basis, requiring careful coordination to avoid clashes with other trades.
Installation is managed on a floor-by-floor basis, with targets to complete both SFS and façade installation within three weeks per floor. At peak periods, up to 25 Advanced Glass operatives have been deployed on site.
As part of its commitment to innovation and quality, Advanced Glass utilised robotic setting-out technology to mark floor plates, gridlines, and datum points to an accuracy of plus or minus 2 mm. This reduced workload for site engineers and improved productivity for follow-on trades.
The façade systems are designed to meet demanding performance criteria, including:
These requirements were integrated into the design from an early stage to ensure compliance without compromising programme delivery.

Flax Place is an ongoing project, approximately three quarters complete as of January 2026.
To date, all installed façade elements have met their required performance standards.
Feedback from the project team has been highly positive, with the project director commenting on the outstanding service, proactive approach, and overall performance of Advanced Glass.

High-rise SFS and aluminium glazing façade for a build to rent residential scheme in the centre of Leeds.